Q11. What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

 
 
 
 

Q12. What indicates the breaking capacity of a fuse or breaker?

 
 
 
 

Q13. What is the main disadvantage of using a ToR (Top of Rack) design?

 
 
 
 

Q14. The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.
What is the set-up in this data center?

 
 
 
 

Q15. A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.
Should the supplier of the fire suppression system be informed on the design of the racks?

 
 
 
 

Q16. The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?

 
 
 
 

Q17. You are installing new copper cabling.
What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

 
 
 
 

Q18. What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

 
 
 
 

Q19. What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

 
 
 
 

Q20. A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?

 
 
 
 

Q21. Do you need to consider bullet (ballistics) protection when designing a data center?

 
 
 
 

Q22. When installing a raised floor, can we use a spirit level bar to level the floor?

 
 
 
 

Q23. Three data centers are benchmarked on facilities energy efficiency.
Data center A has achieved a PUE of 2.45.
Data center B has achieved a PUE of 1.20.
Data center C has achieved a PUE of 1.90.
Which of the data centers is operating at the highest facility efficiency?

 
 
 
 

Q24. You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

 
 
 
 

Q25. Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
* Rated power: 30 kVA
* Rectifier input voltage: 400 V/3 phase
* Rectifier input power factor: 0.8
* Battery rated voltage: 384 V
* Number of cells: 192
* End of discharge voltage: 308 V
* Inverter output voltage: 400 V/3 phase
* Inverter output power factor: 0.8
What information is missing to perform the battery calculation?

 
 
 
 

Q26. You are allowed to use a calculator for this question.
A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.
The temperature is 20 °C / 68 °F.
The required design concentration is 7%.
The S-Factor is 0.1359 (metric) / 1.885 (imperial).
Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

 
 
 
 

Q27. The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.
What action, if any, should you recommend for the computer room?

 
 
 
 

Q28. In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

 
 
 
 

Q29. What is the calculation for the desired attenuation factor for shielding material?

 
 
 
 

EXIN CDCS Exam Syllabus Topics:

Topic Details
Topic 1
  • Designing and Implementing a Data Centre: In this module, the exam assesses the knowledge of Exin data center professionals tasked with the design and implementation of data centers. Candidates will learn the key principles of creating an efficient data center layout, including considerations for scalability, redundancy, and security.
Topic 2
  • Data Centre Environmental Considerations and Efficiency: This section evaluates the proficiency of data center professionals in addressing environmental factors and promoting efficiency within data center operations. The target audience, including data center managers and engineers, will be tested on their ability to identify and implement measures that enhance energy efficiency, cooling management, and sustainable practices.
Topic 3
  • Data Centre Life Cycle and Standards: This section of the exam measures the skills of data center professionals and covers the various stages involved in the life cycle of a data center, from planning and design to implementation and decommissioning.

 

Get CDCS Actual Free Exam Q&As to Prepare Certification: https://www.examdumpsvce.com/CDCS-valid-exam-dumps.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below